The principle that data centers should pay for the grid upgrades their projects cause is increasingly settled. Working for a developer building large loads in grid operator PJM’s territory, I think that is the right outcome—and we act on it by funding infrastructure required by our own projects rather than shifting those costs to host communities. But cost causation answers only who writes the first check. It does not answer who ultimately receives the value of the asset that check creates when infrastructure financed by one project later serves another customer.
COMMENTARY
That question is now before regulators. In June, the Federal Energy Regulatory Commission (FERC) issued tailored show-cause orders directing PJM and the other regional grid operators to justify or reform their rules for connecting and serving large loads. For PJM, FERC identified potential gaps in how large loads procure transmission service, are studied, trigger network upgrades, and are allocated costs. PJM’s response in these proceedings, and FERC’s action on it, could materially reshape how data centers and other large customers connect to and pay for the transmission system.
For transmission-network costs, PJM’s FERC filing may prove more consequential than any single state policy, while states will continue to control retail tariffs, permitting, tax policy, and other customer obligations.
Who Pays
On the “who pays” question, the direction is clear, and states aren’t waiting. Pennsylvania, New Jersey, and Ohio have taken measures in the past 15 months to keep more of those costs on large-load customers’ bills and off others.
Before those costs can be assigned, engineering studies conducted at the developer’s expense identify the upgrades a project requires. A system impact study models how the new load affects the surrounding network, and a facilities study specifies what must be built. Together, they produce a cost estimate and a construction schedule. Regulators then decide which costs the project actually caused, and federal tariffs and state utility rules determine who pays for them.
Pennsylvania has moved further through Gov. Josh Shapiro’s GRID (Governor’s Responsible Infrastructure Development) Requirements. The governor’s Aug. 18 executive order directs the state’s Department of Environmental Protection to evaluate data center permit applications only after developers have made legally binding commitments to comply with GRID and obtained required local approvals (the order is legally binding for all data center projects in Pennsylvania with a peak electrical demand exceeding 25 MW). The requirements are designed to keep data center-related infrastructure and energy costs from being shifted to other customers while imposing additional obligations around generation, transparency, workforce development, community engagement, and environmental performance.
States are increasingly using minimum-billing commitments, financial security, curtailment provisions, and dedicated large-load tariffs to reduce the risk that other customers subsidize data-center infrastructure. New Jersey’s Data Center Fair Share law, signed July 7, requires data centers to guarantee 85% of requested service for 10 years and puts them ahead of residential customers in the curtailment order during grid emergencies. In Ohio, regulators approved a tariff requiring data centers served by the state’s largest utility to pay for at least 85% of their contracted capacity every month for 12 years, whether they use it or not.
When Funded Infrastructure Becomes Shared
Once a customer funds an upgrade, the harder issue is what happens if other grid users later benefit from the capacity that customer created. Generation interconnection rules already include reimbursement and cost-sharing mechanisms in some circumstances when subsequent projects use network capacity funded by earlier projects. Comparable protections for large loads are much less developed.
That distinction matters because utilities often build facilities with more capacity than the first customer immediately needs. A data center may therefore fund a substation, line extension, or network upgrade that later provides headroom for another customer. The unresolved question is not whether the first project should pay for the infrastructure it causes; it is whether that first project should remain the sole payer after the infrastructure effectively becomes shared.
Today, there’s no established route for the original customer to recover any of that cost, and whether one should exist for large loads is among the questions FERC put to the regional operators in June.
Some of the variation in policies reflects who actually has authority over what. States control permits and tax codes. Shapiro’s executive order, for example, removed expedited permitting for data centers and directed his energy counsel to seek state utility rules assigning certain regional reliability costs directly to them.
Creating a Fair Framework
The principle is right: large loads should pay the costs they cause. But cost causation should not become permanent cost assignment when infrastructure funded by one customer later becomes shared infrastructure. PJM and FERC now have an opportunity to solve both sides of that equation—protecting existing customers from subsidy while creating a fair framework for the capital that large-load developers put into the grid.
—Christopher Ruppel is senior vice president of Power at Keel Infrastructure, which develops and owns digital and energy infrastructure across North America, including sites in PJM territory in Pennsylvania.