South Carolina Gov. Henry McMaster (R) wants to sell Santee Cooper, the state-owned utility, even as state lawmakers discuss how to deal with the group’s involvement in the abandoned V.C.…
Santee Cooper
Energy Secretary Rick Perry said in a statement that the “future of nuclear energy in the United States is bright” as his agency on September 29 announced another $3.7 billion…
SCANA Corp. and Santee Cooper moved to cash in a $2.2 billion settlement with Toshiba—even though it will cost them $171 million—rather than risk collecting guaranty payments from the Japanese…
SCANA Corp.’s troubles concerning its decision to abandon the V.C. Summer nuclear expansion intensified again this week after South Carolina’s attorney general’s office and state lawmakers urged state law enforcement…
SCANA Corp. and Santee Cooper—utility partners that recently abandoned a two-unit expansion at the V.C. Summer nuclear plant—have received federal subpoenas for documents associated with a much-guarded February 2016 assessment…
A lawsuit filed in South Carolina wants state-owned utility Santee Cooper to sell the parts from a coal-fired power plant project it suspended in 2009, saying customers should receive the…
SCANA Corp. is withdrawing a petition submitted to regulators seeking to abandon the construction of Units 2 and 3 at the V.C. Summer Nuclear Station in South Carolina. The company’s…
SCANA Corp. and Santee Cooper have ceased construction of Units 2 and 3 at the V.C. Summer Nuclear Station in South Carolina. The project owners said the decision, prompted by…
SCANA Corp. subsidiary South Carolina Electric & Gas Co. (SCG&E) and Santee Cooper—owners of the two-unit expansion of the V.C. Summer nuclear plant—have extended an interim assessment agreement with Westinghouse to…
Delays and other contested costs are expected to push the price for two new units being constructed at the V.C. Summer Nuclear Generating Station up by $980 million, a petition…