The installation of more than one million solar photovoltaic (PV) modules at Sempra U.S. Gas and Power’s and Consolidated Edison Development’s 250-MW AC Copper Mountain Solar 3 project in Boulder City, Nev., was completed in early April. Cupertino Electric and Amec Foster Wheeler said on April 6 that the last module was put in place at the 1,400-acre, fixed-tilt, ground-mount project that broke ground in early 2013 (Figure 5).
—Sonal Patel, associate editor