GE helps CPHGC in Pakistan achieve major power plant milestone three months early

  • Grid synchronization fast-tracked in only 27 months after notice to proceed
  • New plant will provide 1,320 megawatts (MW) to help Pakistan address its growing energy needs and build energy independence

SWITZERLAND, Baden: 27 March 2019 – The first of two supercritical turbines from GE Steam Power has successfully synchronized to Pakistan’s national grid at China Power Hub Generation Company’s (CPHGC) new power plant three months ahead of schedule.

The 1,320 MW plant is located 25 kilometers southwest of the town of Hub, in Pakistan’s Balochistan province, and is a joint-venture project between China Power International Holding Limited (CPIH) and Pakistan’s Hub Power Company (HUBCO).

This important milestone was met just 27 months after the project first received go-ahead. Under an agreement signed in 2016, GE is supplying the core power generation equipment for the project, which comprises two units each of supercritical boilers, steam turbine and generator sets. The project’s engineering, procurement and construction (EPC) contractors are Northwest Electric Power Design Institute Co. Ltd. (NWEPDI) and Tianjin Electric Power Construction Company (TEPC).

“This is a world-class example of GE’s global engineering, manufacturing and execution teams working closely together along with our customers to beat an already ambitious delivery schedule,” said Andreas Lusch, President & CEO of GE Steam Power. “Reaching this key milestone early required a very high degree of technical, engineering and production coordination between our factories in Wuhan and Beijing, China and Wroclaw, Poland with the highest commitment to quality and on-time delivery for our customers.”

“CPHGC is the first overseas thermal power project developed by State Power Investment Corporation under the Belt & Road Initiative. The 2X660MW Coal-Fired Power Project is a priority project under the China Pakistan Economic Corridor,” said Mr. Zhao Yonggang, CEO, CPHGC. “It is testimony to our strong and close partnership with GE that we managed to reach this point well-ahead of schedule. We look forward to continuing our meaningful partnership with GE that promises to be beneficial for the power sector of Pakistan.”

Construction of the CPHGC power plant at Hub began in March 2017 and is expected to begin commercial operation later this year. The plant is one of the infrastructure ventures supported under the China Pakistan Economic Corridor. This development ‘megaproject’ will connect Gwadar Port in southern Pakistan to Xinjiang, China’s northwestern autonomous region, through transportation and energy networks.

The project will support faster socio-economic development by helping to meet the country’s growing energy needs. It will also help Pakistan diversify its energy mix and reduce dependence on expensive imported fuels, allowing the use of cheaper supplies of coal.

About GE Steam Power:
GE Steam Power is an industry leader in cleaner power generation, supporting customers with everything from full turnkey plants to individual components, upgrades, and core operations and maintenance services for their coal and nuclear power plants. As today’s #1 steam franchise with more than 30% of the world’s steam turbine capacity, 50% of the world’s steam turbines for nuclear power plants and 30% of the world’s boilers, GE Steam Power is delivering solutions that ensure a productive future for power plants all over the world.