There has been a major shake up in the contractors involved in both of the new AP1000 nuclear power plant projects under construction in the U.S. Westinghouse Electric Co. LLC,…
CBI
With all 40 remaining construction milestones for V.C. Summer Nuclear Station Units 2 and 3 behind schedule (33 by more than 18 months) as of June 30, South Carolina Electric…
In-service dates for two nuclear units under construction at Plant Vogtle in Georgia have been moved out to December 2017 and December 2018, and the total project cost is now…