Mississippi Power
-
Coal
Kemper County IGCC Plant Generates First Syngas-Fueled Power
Mississippi Power’s integrated gasification combined cycle (IGCC) plant in Kemper County, Miss., on October 12 has begun generating its first power using a combination of syngas (produced from locally mined lignite) and natural gas. The milestone is a major one, said Thomas Fanning, CEO of Mississippi Power’s parent company Southern Co. “After decades of research […]
-
Coal
Delayed Again, Kemper County IGCC Plant to Start Operations in a Month
Mississippi Power’s integrated gasification combined cycle (IGCC) power plant under construction in Kemper County, Miss., will likely be placed in service by November 30, a month later than anticipated. The delay will be costly. Mississippi Power reached a new milestone on September 16, announcing that it had started producing syngas using the second gasifier—gasifier “A”—at […]
-
Coal
Kemper IGCC In-Service Date Pushed Back by a Month
Mississippi Power has pushed back the in-service date of its much-delayed Kemper County integrated gasification combined cycle (IGCC) plant by a month, to October 31, 2016. Initial production of syngas at the plant began on July 14, and testing continues of gasifier B and related lignite feed and ash systems. “The schedule extension provides for […]
-
Legal & Regulatory
Amid Scrutiny, Kemper IGCC Project Marks Big Syngas Production Milestone
Southern Co.’s Kemper County energy facility—the only carbon capture and storage (CCS) integrated gasification combined cycle (IGCC) power plant that is under construction—is producing syngas using lignite. The plant marked its most significant milestone to date on July 14, said Southern Co.’s Mississippi Power. It means that the first-of-its-kind technology to convert locally mined lignite […]
Tagged in: -
Coal
Southern Co. Kemper IGCC Delays, Cost Surges Are Under SEC Scrutiny
The U.S. Securities and Exchange Commission (SEC) is conducting a formal investigation concerning costs and delays plaguing Mississippi Power’s Kemper integrated gasification combined cycle (IGCC) plant. Southern Co., Mississippi Power’s parent company, revealed the investigation in a recent 10-Q financial filing. The company said that while it is fully cooperating with the SEC, it believes the […]
-
Coal
Kemper County IGCC Costs Rise and Delays Loom—Again
In what has become a regular occurrence with the Kemper County integrated gasification combined cycle power plant, Mississippi Power announced in a filing with the Securities and Exchange Commission on April 1 that costs have risen from the most recent projections and further delays in its in-service date are possible. Though the $18 million in […]
-
Coal
Kemper IGCC In-Service Date Pushed to Q3, Costs Surge Again
Mississippi Power’s lignite-fired Kemper County integrated gasification combined cycle (IGCC) power plant is seeing yet another delay and $110 million in new costs, a filing with state regulators shows. The company’s December 2015 monthly status report for the nation’s first commercial power plant that will capture and store carbon dioxide anticipates that it will now […]
-
Coal
Kemper IGCC Celebrates Key Milestone, Suffers New Cost Increases
Mississippi Power has revealed a new cost increase of $110 million for its Kemper County integrated gasification combined cycle (IGCC) facility. But, the company said that it has tested one of two gasification units—reaching what it says is the project's "most significant milestone yet"—and that it does not expect any new delays. Testing the gasifiers […]
-
Coal
Kemper County IGCC Project Costs Soar to $6.1B
Cost estimates for the Kemper County Integrated Coal Gasification Combined Cycle project (IGCC) have surged another $330 million since August, mostly owing to delays that have shifted the plant’s in-service date to the first half of 2016. Plant owner Mississippi Power’s latest monthly report submitted to the Mississippi Public Service Commission shows that the project’s total […]
-
Power
POWER Digest (October 2014)
Kemper County Combined Cycle Unit Begins Commercial Operation. Mississippi Power on Aug. 14 marked a significant milestone and started commercial operation (on natural gas) of the combined cycle unit at the