Kemper
-
Coal
More Delays at Kemper as $250 Million Deadline Looms
Southern Co. has once again moved back the in-service date for the Kemper County integrated gasification combined cycle (IGCC) plant under construction in Mississippi, this time to December 31, the company said in its quarterly report released on November 4. Though the plant has experienced ongoing construction delays for a variety of reasons, the most […]
Tagged in: -
Coal
Kemper IGCC In-Service Date Pushed Back by a Month
Mississippi Power has pushed back the in-service date of its much-delayed Kemper County integrated gasification combined cycle (IGCC) plant by a month, to October 31, 2016. Initial production of syngas at the plant began on July 14, and testing continues of gasifier B and related lignite feed and ash systems. “The schedule extension provides for […]
-
Legal & Regulatory
Amid Scrutiny, Kemper IGCC Project Marks Big Syngas Production Milestone
Southern Co.’s Kemper County energy facility—the only carbon capture and storage (CCS) integrated gasification combined cycle (IGCC) power plant that is under construction—is producing syngas using lignite. The plant marked its most significant milestone to date on July 14, said Southern Co.’s Mississippi Power. It means that the first-of-its-kind technology to convert locally mined lignite […]
Tagged in: -
Coal
Southern Co. Kemper IGCC Delays, Cost Surges Are Under SEC Scrutiny
The U.S. Securities and Exchange Commission (SEC) is conducting a formal investigation concerning costs and delays plaguing Mississippi Power’s Kemper integrated gasification combined cycle (IGCC) plant. Southern Co., Mississippi Power’s parent company, revealed the investigation in a recent 10-Q financial filing. The company said that while it is fully cooperating with the SEC, it believes the […]
-
Coal
Kemper County IGCC Costs Rise and Delays Loom—Again
In what has become a regular occurrence with the Kemper County integrated gasification combined cycle power plant, Mississippi Power announced in a filing with the Securities and Exchange Commission on April 1 that costs have risen from the most recent projections and further delays in its in-service date are possible. Though the $18 million in […]
-
Coal
Kemper IGCC In-Service Date Pushed to Q3, Costs Surge Again
Mississippi Power’s lignite-fired Kemper County integrated gasification combined cycle (IGCC) power plant is seeing yet another delay and $110 million in new costs, a filing with state regulators shows. The company’s December 2015 monthly status report for the nation’s first commercial power plant that will capture and store carbon dioxide anticipates that it will now […]
-
Coal
Kemper IGCC Celebrates Key Milestone, Suffers New Cost Increases
Mississippi Power has revealed a new cost increase of $110 million for its Kemper County integrated gasification combined cycle (IGCC) facility. But, the company said that it has tested one of two gasification units—reaching what it says is the project's "most significant milestone yet"—and that it does not expect any new delays. Testing the gasifiers […]
-
Coal
DOE Funds New Gasification Projects As Existing IGCC Projects Face Turmoil
Seven gasification projects will receive about $7.5 million in funding from the Department of Energy’s (DOE’s) National Energy Technology Laboratory. The projects will reduce the cost of coal conversion and mitigate the environmental impacts of fossil-fueled power generation, the DOE said in a statement on July 14. The projects fall under two subtopic areas: development […]
Tagged in: -
Coal
Kemper Project Loses Key Power Buyer Due to Delays, High Costs
South Mississippi Electric (SME), an electric cooperative that has been Mississippi Power Co.’s (MPC’s) long-time backer in the development of the Kemper energy facility, has pulled out of the project, citing delays in project schedule and increased participation costs as reasons for its withdrawal. The cooperative that generates and transmits electricity for 11 member cooperatives […]
-
Coal
Kemper IGCC Costs Again Revised Upwards, In-Schedule Date Reset
The total costs of Mississippi Power’s Kemper County integrated gasification combined cycle (IGCC) plant—the nation’s only large-scale integrated carbon capture and sequestration project (CCS) under construction—have now almost doubled to $4.02 billion. A review of the Kemper facility’s construction schedule and costs completed this month by Mississippi Power management prompted the company to push back […]