Valley Energy Center


New York Gas Plant Comes Online Despite Opposition

The Valley Energy Center in Orange County, New York, entered commercial operation on October 1 despite complaints from local officials and area residents about noise from the plant, among other…


Judge Rules New York Gas Plant Can Resume Startup Tests

A New York Supreme Court judge on August 15 said Competitive Power Ventures (CPV) can resume startup tests at its new natural gas-fired power plant in Wawayanda. The decision Wednesday…


New York Denies Air Permit for New Gas-Fired Power Plant

A natural gas-fired power plant in New York state that planned to ramp up to full operations this month has been denied an air quality permit from state officials. Competitive…