expansion
-
Nuclear
Russia Has Deal to Build Eight Nuclear Power Plants in Iran
The president of Iran’s nuclear energy agency said officials in that country have signed an agreement with Russia for construction of at least eight nuclear power plants in Iran. Mohammad Eslami, president of the Atomic Energy Organization of Iran (AEOI), confirmed the deal on June 9 during a visit by members of the Iranian parliament’s […]
-
Nuclear
Georgia Power Moves Closer to Loading Fuel in Vogtle Unit 4
The oft-delayed two-unit expansion of the Vogtle nuclear power plant in Georgia took another step forward on July 21, as Georgia Power said several tasks needed for Unit 4 at the site have been completed and the company is readying the reactor for fuel loading. The utility on Friday announced that Southern Nuclear, part of […]
-
Nuclear
Vogtle Expansion Cost Jumps Again; In-Service Dates Set for 2023
Southern Co. on July 28 increased its cost estimate for Georgia Power’s share of the two-unit expansion of the Vogtle nuclear plant. Southern, during an investor presentation of the company’s second-quarter financial results, said Georgia Power’s share of capital costs for the project has risen by $52 million, to about $10.5 billion in total. Georgia […]
-
Nuclear
Vogtle Nuclear Expansion Price Tag Tops $30 Billion
An updated financial report from one of the owners of the Plant Vogtle nuclear expansion in Georgia shows the cost to build two new reactors has now topped $30 billion, more than double the original price tag expected for the project. The Municipal Electric Authority of Georgia (MEAG), one of four groups with an ownership […]
-
Nuclear
Southern CEO: Vogtle Still on Track for 2022-2023 Start
Southern Co. CEO Tom Fanning said the group continues to stick to its most-recent timeline for startup of the two-unit expansion of the Vogtle nuclear plant in Georgia, telling participants in the company’s first-quarter 2022 earnings call that construction is pacing well, with fuel load for Unit 3 expected later this year. “Importantly, the […]
-
Press Releases
Micatu Completes New Offices, Launches Construction on One of the Nation’s Largest Optical Sensing Manufacturing Facilities for Grid Applications
Total expansion adds 40,000 square feet of space for additional staff, training, manufacturing, a clean room, and outdoor grid distribution testing lab CORNING, NEW YORK, (November 19, 2021) – Micatu Incorporated, a leader in cutting-edge optical sensing technology, finalized Phase I of its expansion with the completion of a new office and training space in upstate New York. The […]
-
News
Vogtle Start Dates Pushed Back Again
Georgia Power has again pushed back the in-service dates for two new reactors at the Vogtle nuclear power plant, with Units 3 and 4 now projected to come online in the third quarter of 2022 and the second quarter of 2023, respectively. Georgia Power in an Oct. 21 news release said its needs more time […]
-
Nuclear
Former SCANA CEO Will Land in Prison as Result of V.C. Summer Nuclear Project
Kevin B. Marsh, former CEO of SCANA Corp., was sentenced to two years in federal prison after pleading guilty to conspiracy to commit mail and wire fraud related to the V.C. Summer nuclear expansion project. Marsh is the first defendant in the case to be sentenced as a result of the investigation. However, the U.S. […]
-
Nuclear
More Vogtle Delays; Experts Target Mid-2022 Startup at Earliest
Engineering experts and financial consultants involved with oversight of the two-unit expansion of the Vogtle nuclear power plant in Georgia said the project’s startup now likely will be delayed until the summer of 2022. They also said the project faces more cost overruns. In testimony filed June 7 with the Georgia Public Service Commission, the […]
-
News
Southern Announces Delay in Testing at Vogtle
Southern Co. has announced another delay in hot functional testing for the first unit of its two-unit expansion at the Vogtle nuclear plant in Georgia. The utility in a March 19 filing with the U.S. Securities and Exchange Commission said its subsidiary Georgia Power “now expects the start of hot functional testing for Unit 3 […]
-
Nuclear
Vogtle Receives First Shipment of Nuclear Fuel
The two-unit expansion of the Vogtle nuclear power plant in Georgia reached another milestone as Georgia Power received the first shipment of nuclear fuel for Unit 3 of the project. The utility on Dec. 9 said receipt of the fuel follows completion and inspection of several construction areas at the site in Waynesboro, Georgia. Those […]
-
Nuclear
More Delays for Vogtle Plant Expansion
Georgia Power said it still expects to meet a state regulatory deadline for commercial operation of the first of two new reactors at its Vogtle nuclear plant expansion. The utility, though, on Oct. 22 acknowledged it has pushed back some aspects of the project, including delaying the loading of nuclear fuel for the first reactor […]
-
Nuclear
Southern: Vogtle On Track for November 2021 Startup
Southern Co. says it remains on schedule to complete Units 3 and 4 of the Vogtle nuclear expansion project by November 2021 and November 2022, respectively, despite the impacts of the COVID-19 pandemic. The company in its 2020 second-quarter earnings report on July 30 said issues associated with the coronavirus have increased subsidiary Georgia Power’s […]
-
Nuclear
Last Major Module Received at Vogtle Nuclear Site
The final major module needed to construct Vogtle Units 3 and 4—the only new commercial nuclear power units currently under construction in the U.S.—has arrived at the site near Waynesboro, Georgia. That means all 1,485 major modules have been manufactured and safely delivered to the project. Georgia Power announced the milestone in a press release […]
-
Legal & Regulatory
Georgia PSC Chair: We Wanted Vogtle to Go Forward
Georgia Public Service Commission (PSC) Chairman Stan Wise said his agency was “not going to make a decision to discontinue” construction of two new nuclear reactors at Plant Vogtle, instead putting the decision squarely in the hands of Southern Co. and Georgia Power at the PSC’s December 21 meeting to determine the fate of the […]
-
Nuclear
Southern Company Could Delay Plant Vogtle Decision Until Late Summer
CEO Tom Fanning told Southern Co.’s shareholders attending the company’s annual meeting on May 24 that a decision on how to proceed with the Plant Vogtle nuclear expansion could take several more months. The Vogtle expansion—one of two new nuclear construction projects underway in the U.S. utilizing Westinghouse’s AP1000 technology—has been in limbo, albeit still in […]