Watts Bar Unit 2 Nuclear Plant Completes Power Ascension Testing
The Tennessee Valley Authority (TVA) has reached another milestone in its effort to bring Watts Bar Unit 2 into commercial operation: The unit completed its final power ascension test—a 50% load rejection from full power—and safely returned to full power on September 30. The testing had been halted on August 30 due to a switchyard […]
-
Nuclear
Transformer Fire Will Delay Watts Bar Unit 2 Commercial Operation
A main bank transformer fire has put a halt to power ascension testing at the Tennessee Valley Authority’s (TVA’s) Watts Bar Unit 2 nuclear plant. The incident occurred at about 9:10 p.m., on August 30, when an electrical fault on the 2B main bank transformer caused the Unit 2 main turbine to trip. The reactor, […]