SRP Warns Arizona Regulator Reliability at Risk by 2024 Without Gas Plant Expansion
Salt River Project Agricultural Improvement and Power District (SRP) is seeking a rehearing and reconsideration of the Arizona Corporation Commission’s (ACC’s) denial of a major gas power plant expansion, which the public power utility has stressed will be crucial for near-term system reliability and long-term renewable integration. In a filing on May 16, SRP urged […]
-
Gas
SRP Approves Arizona Expansion with 16 Gas-Fired Turbines
The board of directors of Arizona’s second-largest public utility has approved a nearly $1 billion plan to expand the natural gas-fired Coolidge Generating Station, adding 820 MW of generation capacity. The Coolidge station at present is a 575-MW power plant with 12 single-cycle gas turbines; the plant began operating in 2011. The expansion plan approved […]