Modular Design Simplifies Development
One of Sempra’s goals in constructing El Dorado was to gain experience with the design and operation of a "small" PV project before moving ahead with plans for larger systems (see sidebar). Sempra’s market plan, however, is much different from those of merchant plant developers chasing opportunities who, more often than not, end up with little to show for the effort. Instead, Sempra envisions that PV projects can be successful and economic to operate if they are constructed adjacent to existing power facilities.
Many synergies can be enjoyed by colocating PV projects with existing plants. El Dorado Energy Plant Manager Kevin Gillespie pointed out that by leveraging their highly qualified and experienced combined-cycle plant operating and maintenance staff, they have reduced the PV plant’s operating costs and improved reliability. Leveraging the plant’s transmission interconnection also gives the PV plant a significant economic advantage over other merchant plant developers in time and cost.
Gallagher also pointed out that by modularizing the plant’s design into 1-MW blocks, Sempra is able to quickly capture and transfer lessons learned to the design and construction of future projects.
In my opinion, Sempra has quickly established perhaps the most rational development program for PV technology development in the U.S. and is on the road to positioning itself as preeminent PV system developer. Gallagher was quick to note that when El Dorado was conceived, there were another 13 PV projects in the NV Energy queue looking for an interconnection agreement. (El Dorado is in the NV Energy service territory, so the plant’s physical interconnection is to NV Energy’s grid.) A year later, all 13 of those projects had been delayed or abandoned; only El Dorado was actually built.
At El Dorado, all the energy produced by the PV field connects directly to the main 4,160-kW bus of the adjacent combined-cycle plant and the plant switchyard. Additionally, the combined-cycle plant’s distributed control system is completely integrated with the PV plant (Figure 3). A single technician manages all aspects of the PV plant, while First Solar provides maintenance and remote monitoring as part of its ongoing support contract. In addition, other technicians have been cross-trained to operate the PV plant.

3. Tightly knit system. The combined-cycle plant control room staff can monitor the performance of the entire PV plant on a single monitor. This monitor reports that the PV system was producing 9,585 kW when the photo was taken. The remainder of the screens report on the performance and control the 2 x 1 combined-cycle plant. Source: POWER