Demandbase Connect

June 1, 2009

Steam Turbines: San Onofre Nuclear Generating Station Gets Upgraded Generator Rotors

RSS
Pages: 12

Southern California Edison’s (SCE) 2,250-MWe San Onofre Nuclear Generating Station (SONGS) recently took receipt of a new and upgraded generator rotor for one of its two Alstom steam turbine generator units (Figure 1). Following the successful installation and flawless start-up of this new rotor in the Unit 2 generator, the former Unit 2 rotor was transported to Alstom’s workshop in Richmond, Va., for refurbishment and rewinding. The refurbished Unit 2 rotor was then shipped back to California and installed in the Unit 3 machine during the plant’s fall 2008 refueling outage. Following this second rotor switch and the successful return to service of Unit 3, the original Unit 3 rotor was packed for long-term storage and is being retained on site as an emergency spare.

1. Ocean view property. San Onofre Nuclear Generating Station, located along the beautiful California coast between San Diego and Los Angeles, has two 1,200-MW pressurized
water reactors that needed generator rotor upgrades. The plant is jointly owned by Southern California Edison (78.21%), San Diego Gas & Electric (20%), and the city of Riverside
(1.79%). Source: Nuclear Regulatory Commission

According to SONGS Project Manager Fred Simma, "Moving parts age and wear out. Our SONGS generators are more than 25 years old, and since the average life of a large rotor is about 20 to 25 years, we have to be mindful of reliability."

The SONGS Unit 3 generator rotor electrical performance had degraded over the years and was showing increased vibration, particularly with step increases in April and October 2003 caused by severe grid disturbances. Various options were considered, but the most cost-effective solution was to purchase a replacement rotor for Unit 2 and subsequently refurbish and rewind the Unit 2 rotor for installation into Unit 3.

Phase 1: Replace Unit 2 Generator Rotor

The rotor purchase order was released in 2004, which initiated a series of manufacturing steps that spanned the globe. The rotor forging was manufactured in Japan; then shipped to Birr, Switzerland; then Stafford, England; then Richmond, Va.; and finally to San Clemente, Calif., for installation.

The rotor forging was manufactured by Japan Steel Works Ltd.’s facilities on the island of Hokkaido over the first 18 months of the project (Figure 2). In late spring 2005, the rotor forging was shipped to Alstom’s facilities in Birr for machining (Figure 3). In the winter of 2005, the rotor was then transported to Alstom Power in Stafford for installation of the windings, using the latest advances in insulation material for consolidated coil technology (Figure 4).

2. Packed and ready. Generator rotor forging for San Onofre Nuclear Generating Station Unit 2 en route from Japan Steel Works Ltd. to Birr, Switzerland. Courtesy: Alstom


3. Time slot. The finished turned rotor was loaded into a large milling machine at Alstom’s Birr facility, ready for cutting the rotorwinding slots. Courtesy: Alstom


4. Tightly wound. The machined rotor for Unit 2 was wound in Alstom’s Stafford, England, facility. Courtesy: Alstom

The new Alstom replacement rotor was able to provide SCE with numerous enhancements over the existing plant equipment as a result of design and material developments and improvements in computerized design tools since the original equipment had been supplied.

The new rotor was manufactured from a higher-material-strength steel forging than was previously achievable, and slight changes were made to various shaft machining features to enable improved stress distribution characteristics. One example of this was where the use of modern three-dimensional finite element analysis tools enabled an improved retaining ring – to – rotor body shrink interface and more effective damper circuit to be developed. The improved design, using Alstom’s consolidated coil technology, provided increased mechanical and dielectric strength of the rotor winding insulation components and provided SCE with an additional balance plane and differential expansion measurement facility.

In the summer of 2006, the rotor was shipped to Portsmouth, Va., for delivery to the Alstom Service Workshop facility in Richmond for final detailed work. Shipping a partially completed generator rotor weighing nearly 200 tons across the ocean was anything but simple. The rotor, plus a 20-ton container, was shipped to the U.S. on a roll-on/roll-off ocean-transport vessel.

Alstom had originally planned to transport the rotor across the port from Portsmouth to Newport News, Va., via a floating crane, but decided that too much risk was involved. Instead, the rotor was very slowly and carefully slid onto a rail car with a "jack-and-slide" system. GPS impact recorders were installed on the rotor’s container in order to help continually track the location of the car and detect any impacts the flat car may have experienced. The rotor arrived safe and sound at the Richmond facility and was unloaded by the facility’s 275-ton crane.

Over a six-week period, Alstom’s turbine and generator services performed prebalancing, machining, final testing, and high-speed balancing. "We had seen the specifications," said Jim Donnelly, Alstom project manager, "but you don’t realize how big it is until you see it in real life. We often service 40-, 50-, and 60,000-pound rotors, so this was much more of a challenge."

Lathe work involved installing the rotor and then performing incoming run-outs, machining the coupling, polishing seal diameters, and checking rotor blade tips (Figure 5).

5. Lathe work. The rotor underwent on-receipt run-out checks and coupling finish machining at Alstom’s Richmond, Va., service facilities. Courtesy: Alstom

The next phase involved millwork: a combination of drilling and tapping coupling drive pinholes and installing adapter plates, along with the installation of 54-inch- and 76-inch-diameter fan hubs and blades. After more lathe work, the rotor was placed in the balance pit for balancing, overspeed testing, and two heat runs (Figure 6). After final run-out measurements and checking, the rotor was packed for long-term storage and carefully placed back on the rail car.

6. Heavy lift. Alstom’s Richmond facility completed the final machining, assembly, balancing, and acceptance testing. The 350-ton-capacity high-speed balancing facility is one of the largest in North America. Courtesy:Alstom

In early fall 2006, the rotor was transported by rail flatcar via CSX to Louisiana, where it was shifted to Union Pacific. A surveyor accompanied the rotor to help ease the transition in the rail yards and make sure it was safely delivered to the plant (Figure 7).

7. Home at last. The new generator was delivered to SONGS Unit 2. The Unit 2 generator shaft was sent to Alstom for refurbishment prior to installation in Unit 3. The old Unit 3 shaft will be kept on site as an emergency replacement. Courtesy: Alstom

Pages: 12


 

Related Stories








Subscribe to POWERnews

First Name Address Email Last Name City Company
Title
State      Zip Code




© 2012 Tradefair Group, an Access Intelligence LLC company.