Advanced Rebuilding Techniques Enable Quick Rebuilds
The rebuilding process begins with testing and a troubleshooting analysis of the heater. Sophisticated equipment determines the exact location, nature, and severity of a problem via eddy current, ultrasonic, dye penetrate, magnetic particle, hydrostatic, and boroscopic testing procedures.
With testing data in hand, a rebuilding company can make recommendations on cost-effective options for remedial correction, retubing to original specification, or rebuilding to improve performance.
Specialized tools have done much to speed up the process. Hydraulic tube pullers, power tube strippers, tube joint milling tools, and plasma arc inner-diameter tube-cutting facilitate the rebuilding process. Additionally, new technology allows for defective or leaking tubes to be explosively plugged with the unit online by utilizing a robotic arm to install the required tube plugs. Doing so provides a safer method of installing tube plugs that keeps personnel out of harm’s way.
Rebuilding Cost-Savings in Practice
Founded in 1989, NRG Energy Inc. is a wholesale power generation company, primarily engaged in the ownership and operation of power generation facilities and the sale of energy, capacity, and related products in the U.S. and internationally. The company’s global portfolio of projects totals more than 24,000 MW.
NRG’s Limestone station, located between Houston and Dallas, is a coal-fired plant with two units: 836 MW and 864 MW. Both of the original equipment manufacturer’s heaters had been in service for more than 20 years. However, the desuperheater was a little too large, resulting in saturated water exiting at excessive velocities that caused tube erosion.
"We initially considered buying completely new heaters, but ultimately decided not to because of the additional cost," Samford explained.
APS began the repair process with a failure analysis that identified vibration in the desuperheating zone as a cause of tube failures (Figure 1). APS then redesigned the desuperheater to eliminate the wet wall condition of the tubes and to reduce the velocity of the steam entering the desuperheater while maintaining the original design thermal and operational parameters.

1. Just worn out. Damage to the desuperheater tubes due to steam impingement in this feedwater heater caused a reduction in plant efficiency. Courtesy: American Power Services
Work began in late February 2009. The internal structure was rebuilt while changing the steam inlet location. Additionally, the desuperheater flow path was rerouted during the rebuilding process.
In order to speed up the process, a specialized motor-driven plasma arc cutter was used to remove the hemispherical head in order to facilitate better access to the tubesheet during the rebuilding process (Figure 2). The additional space directly led to a more efficient rebuilding project by providing full access to the tubesheet (Figure 3). This allowed the use of efficient tools to quickly pull the tube stubs, weld the new tubes to the tubesheet, and mechanically expand the tube ends into the tubesheet.

2. Cutting-edge repair. In order to speed up the rebuilding process, a specialized motor-driven plasma cutter was used to remove the hemispherical head to give better access to the tube sheet. Courtesy: American Power Services

3. Clear a path. The additional space provided by removal of the hemispherical head allowed a more efficient rebuilding project by providing full access to the feedwater heater’s tubesheet. Courtesy: American Power Services
The rebuilt feedwater heaters allowed the Limestone plant to run at design superheat conditions, thereby eliminating the wet wall condition (Figure 4). As a result, either of the two units can be taken off-line and the plant can still generate 100% power output. Since the condensing zone steam velocity was increased, thermal efficiency improved slightly. The job was finished within 25 days.

4. Better-than-new condition. APS undertook the rebuilding project using its ASME Code shop and 50 certified and trained heat exchanger technicians and code welders, plus its nondestructive examination staff. The feedwater heater retubing was completed during a scheduled four-week outage. Courtesy: American Power Services
"By rebuilding over buying a new unit, we saved our company money," says Samford.
— Contributed by American Power Services (www.1aps.com).