Banking on new turbines
The Burbo Bank installation is the first offshore project using the 3.6-MW Siemens Power Generation (SPG, www.powergeneration.siemens.com) SWT-3.6-107 turbines. SPG supplied and installed the 25 turbines on a 4-square-mile lease in the Burbo Flats in Liverpool Bay at the entrance to the River Mersey, approximately 4 miles from the Sefton coastline. The Burbo Banks, once feared by seamen for strong winds and shallow depths, is an excellent location for a wind farm for those very same reasons (see box). The 90-MW wind farm is operated by SeaScape Energy Ltd., a company owned by DONG.
Each wind turbine assembly consists of the turbine, blades, and nacelle; a support tower; and a foundation. Each turbine is configured with a 350-foot-diameter three-bladed rotor with blades 172 feet long (Figure 2). The rotor assembly is connected directly to the gearbox and generator contained in the nacelle and mounted on top of a 210-ft tower (Figure 3). Each tower supporting a turbine is anchored to the seabed by a foundation consisting of a single monopile structure over 16 ft in diameter and over 170 ft tall. The foundation is driven up to 80 ft into the seabed such that it extends 56 ft above mean sea level. The turbines are spaced between 1,750 and 2,400 ft apart.

2. A tale of three blades. Siemens uses a three-bladed turbine design. Each blade is over 170 feet long and is connected to the turbine hub at sea. Courtesy: Siemens Power Generation

3. Mini power plant. The turbine nacelle houses the gearbox, generator, and controls and was preassembled onshore. The entire assembly was then lifted and attached on top of a 210-foot support tower. Courtesy: Siemens Power Generation
SPG leased an 11-acre parcel in the port of Mostyn, located in North Wales, where preassembly of the turbines began in early May. The turbine parts were carried on the BBC Mississippi from Denmark, north around Scotland, and to Mostyn. The cargo ship was able to pack parts for six and a half complete turbine assemblies per trip; heavy parts were stored under deck and the lighter parts were in racks on the deck.
At Mostyn, the 210-ft steel support towers were preassembled with all the internal and electrical systems and then tested. Purpose-built vessels were used to ferry the towers, nacelles, hubs, and blades to the site, about 4 miles offshore. Each of the turbines required five heavy lifts spaced over half a day. Some lifts were up to 185 tons. Erection of all 25 turbines was completed in only 43 days (Figure 4).

4. Float like a butterfly. A specially built floating crane was used to lift the nacelle, hub, and blades into place. Note that the nacelle is in place and the crane is in the process of lifting one of the three blades. Courtesy: Siemens Power Generation
Power cables, buried under the seabed, interconnect the turbines and the three cables that bring the power ashore and then underground 3 miles to a substation in Wallasey. The substation steps up the generation voltage (33 kV) to a transmission voltage (132 kV) and feeds it into the national electricity grid. The 24 miles of XLPE (cross-linked polyethylene) armored submarine cable were configured with three conductors with an integrated fiber-optic cable for remote monitoring and control functions. The cable was supplied by ABB of Karlskrona, Sweden.
An operations and maintenance facility was established in Liverpool Harbor to monitor the wind farm’s performance and to provide technicians with access to the turbines by boat for routine inspection and maintenance. These turbines are designed to operate approximately 6,000 hours a year over a 20-year design life.
More offshore in store
“Offshore wind energy is a key future market for Siemens,” said Andreas Nauen, head of the Wind Power Division of SPG.
In 1991, SPG installed the first offshore wind farm in the world in Denmark. The company also teamed with DONG for the North Sea’s Nysted project in 2003. Next year Siemens will start erection work on the largest offshore wind farm in the world, off the east coast of Great Britain. That 180-MW Lynn and Inner Dowsing project will use 54 SWT-3.6-107 wind turbines and will be owned and operated by British Gas’s parent company, Centrica. SPG will be responsible for O&M of the project for its first five years of operation. The overall project cost exceeds $600 million at today’s exchange rates. That project will wrest the title of world’s largest offshore wind project from Nysted.