Coal

Estimating SCR installation costs

The goal of the Clean Air Interstate Rule (CAIR) signed into law almost a year ago is to reduce NOx emissions by 60%, relative to 2003 levels, across 28 eastern states and the District of Columbia by 2015. Though SCR systems worth more than $4 billion are expected to be purchased worldwide next year, in the U.S. more than 40 GW of capacity in CAIR-affected states are expected to be equipped with the technology by 2010.

This increased level of SCR installation activity comes on the heels of the 1995 NOx SIP (State Implementation Plan) Call Rule, which motivated the installation of almost 85 GW of SCR installations at central station steam plants over the past decade. Many utilities will have to place orders this year to comply with the NOx Phase I in-service deadline of 2009. Full implementation of CAIR will occur in 2015. One of the challenges facing utilities affected by CAIR and actively analyzing their cap-and-trade options is to understand the capital costs involved in retrofitting an SCR system.

Survey results

The EUCG, an association of 24 electric utilities representing 302 individual coal-fired units, is a forum through which the utilities can enhance their O&M and construction practices to improve their operational and cost performance.

One vehicle used by the EUCG is member surveys. One recently completed survey focused on SCR system installation costs and the project and design attributes that contribute to them. Specifically, it identified the costs of construction labor; equipment; materials; and project management, engineering, and construction management (PMEC). The survey addressed 11 specific scope/design unit attributes such as the type of ammonia system used, the NOx-removal efficiency design basis of the system, and SCR-related plant upgrades (such as economizer, air heater, and fans) on a $/kW basis.

Responses to the survey yielded scope, cost, and design information on 72 individual units totaling 41 GW (representing 39% of installed SCR systems in the U.S. by MW at the time of the study) owned by eight large utilities from SIP Call states located in the East and Midwest. The sample also reflected the distribution of installations in the U.S., so the survey results can be considered a valid top-level view of system costs.

Economies of scale

As Figure 1 shows, although almost three-fourths of the surveyed units have a capacity of 300 to 900 MW, together they represent only a little over half of the total capacity studied. Overall, costs were reported to be in the $100 to $200/kW range for the majority of the systems (Figure 2), with only three reported installations exceeding $200/kW. System size (with a 644-MW average unit size in the $100 to $150/kW range) seems to dominate; larger average system costs are significantly less than the next survey category (the $150 to $200/kW range, with a 309-MW average unit size). The data also suggest that the larger units were installed earlier: The average unit size retrofit before 2003 was 623 MW, versus 466 MW since 2003.

graph

Source: EUCG Inc.

1. SCR cost survey results. Survey results, categorized by plant size, covered approximately 39% of the new selective catalytic reduction (SCR) capacity installed through early 2004.

 

graph

Source: EUCG Inc.

2. What they spent. Most surveyed utilities spent between $100 and $200/kW for a selective catalytic reduction system.

 

The range of category costs by unit size ($/kW) provides insight into SCR projects’ relative complexities. For example, the aggregated reported costs in the defined categories (Figure 3) point to several conclusions:

graph

Source: EUCG Inc.

3. Cost by unit size. The cost distribution for 72 units with SCR installed shows expected economies of scale.

 
  • The cost of construction labor on smaller projects exceeds the average construction labor cost in all categories by about 50%. The implication is that small plants will be cost-penalized by their lack of economies of scale because they may be more difficult to retrofit.
  • Construction labor costs were relatively constant for plants larger than 300 MW, with an average cost of just over $64/kW.
  • As expected, economies of scale also affect SCR material costs, with larger units costing less to retrofit, on a $/kW basis, than smaller units.
  • Sophisticated regression modeling techniques (multivariate analysis) generally did a poor job of predicting overall installed costs; too many site-specific variables impact construction costs.
  • PMEC costs are relatively consistent regardless of unit size.

The good old days

The survey data also revealed that deviations from average installation costs correlate strongly with project timing, especially for those units installed after 2003 (Figure 4). The significantly higher construction labor costs for later projects most likely reflect increased project complexity—"easier" projects were already completed—but also perhaps increased competition for skilled labor resources as the number of SCR installation projects under way in the U.S. skyrocketed.

graph

Source: EUCG Inc.

4. Timing affected costs. The deviation of category costs as a function of SCR project completion date shows that early adopters paid less than those that lagged behind.

 

Interestingly, the variation in material costs was constant over the survey period, most likely reflecting increased competitiveness among SCR suppliers. By contrast, PMEC costs showed higher variability, which—as in the case of construction labor costs—reflected the greater complexity of later projects. Average cost variation by cost category is summarized in the table.

One survey, many conclusions

Although the survey results provide useful insight into expected installed costs, they also confirm that there is no one-size-fits-all SCR design. What the data also make clear is that site-specific characteristics of units and plants can drive a project’s cost much higher than anticipated. Together, these conclusions suggest that "retrofit difficulty" is indeed relative. Units with a capacity of 600 to 900 MW appear to be more difficult to retrofit than those in other size ranges.

Variation of surveyed cost categories by unit size.  
Source: EUCG Inc.

Because SCRs are unitized, greater economies of scale were expected from the survey results. Some possible explanations for the modest advantage of scale include:

  • The impact of newer plants’ tighter layouts, which often necessitate much more complex duct installations, which raises costs).
  • Plants’ limited ability to use the most cost-effective method of equipment transportation. Some 41% of the units surveyed in the 600- to 900-MW range are close to navigable waters, versus 76% of units larger than 900 MW.
  • The increasingly modular design of SCR systems, which reduces their capital costs but still requires them to be delivered by sea or river.

SHARE this article